My Eco-Maison

An eco-friendly new build in South West France

An eco-friendly new build in South West France

Bathroom / Bedroom Two Walls – 13th & 16th August 2019

Build | Internal Walls – Bathroom & Second Bedroom

Tuesday 13th & Friday 16th August 2019

With Tony working on his own, it made more sense to make progress on the remaining internal walls. There were a couple of issues matching the design plans and the actual alignment of the second bedroom wall.  These were addressed and all but the bathroom upper panels are now in place.

Gallery | August 2019

More Posts...

Quick Search...

Get in Touch...

If you have any questions or general enquiries, please send us a message...

First Name *
Surname *
Email *
Subject *
Message *
* Field is required